30 days.

Explanation:

Before:

One day work = 1 / 20

One man's one day work = 1 / ( 20 * 75)

Now:

No. f workers = 50

One day work = 50 * 1 / ( 20 * 75)

The total no. of days required to complete the work = (75 * 20) / 50 = 30. 